Current positionInstalled steelwork; roof structure next
  1. Complete

    Survey and strip-out

    The existing building was opened up and the old roofs removed.

  2. Current stage

    Steelwork and structural preparation

    Steel beams and goalpost frames are installed, with one further structure described as remaining.

  3. Next stage

    Roof trusses and enclosure

    The new roof structure and enclosure follow the remaining structural work.

  4. Next stage

    Annex, garage and handover

    The planned kitchen, living space, bedroom and en-suite will sit alongside a double garage and separate storage.

Project Overview

LME is carrying out a complete renovation and conversion of a former school toilet and changing block at the Old School House in South Kyme.

The existing concrete roof has been removed and the failed floor will be rebuilt with new hardcore, drainage, insulation and concrete. A goalpost steel structure, new steels and timber trusses will support the new pitched roof.

The finished layout will include a self-contained annex with kitchen and living space, one bedroom, bathroom, dressing area and patio doors, alongside a double garage and separate outside storage.

A closer look at the earlier structural work

The expanded gallery records the strip-out, temporary supports and removal of the former concrete roof. These photographs illustrate the earlier preparation stages of the conversion.

Read behind the build at the Old School House for the photographic story.

Filmed update: steelwork and the planned layout

Lee’s walkthrough shows the installed steels and goalpost structures, with one further steel structure still to be installed before the roof trusses. The central goalpost frame will be built around in brickwork to form the two garage-door openings.

The planned annex includes kitchen and living space, a bedroom and en-suite, with patio doors opening onto a patio. The adjoining area will form a double garage, with separate outside storage or workshop space. An opening used during the work will be closed later.

Lee explained that the old garage roof was a tin structure and the annex had an uninsulated concrete roof. The existing roofs were removed because they were unsuitable for the proposed conversion and its building-regulation requirements. This describes the decision on this building, rather than a rule applying to every outbuilding.

Installed steel beams and internal walls at the South Kyme outbuilding conversion
Installed steel beams and internal walls at the South Kyme outbuilding conversion.

View the South Kyme conversion gallery and explore complete property renovations.

What we did

Strip-out and removal of the existing concrete roof
Replacement hardcore, drainage, insulation and concrete floor
Goalpost structural steelwork
New pitched timber roof
One-bedroom annex with kitchen, living space and bathroom
Double garage and separate outside storage

Project details

TypeRenovation & Conversion
LocationSouth Kyme, Lincolnshire
StatusIn progress
Start a similar project
Related building services
Complete Property Renovations in Lincolnshire→Groundworks & Foundations in Lincolnshire→Residential Development Construction→

Gallery

Aerial view of the open annex and garage structure at the Old School House in South Kyme
Aerial view of the open annex and garage structure at the Old School House in South Kyme.
Installed steel beams and internal walls at the South Kyme outbuilding conversion
Installed steel beams and internal walls at the South Kyme outbuilding conversion.
Overhead view of the Old School House conversion and adjoining buildings in South Kyme
Overhead view of the Old School House conversion and adjoining buildings in South Kyme.
Aerial view of the Old School House outbuilding conversion in South Kyme
Existing concrete roof removed ready for the new pitched roof structure
Former school toilet and changing block before conversion work
Existing internal walls being prepared for the new one-bedroom annex layout
Stripped internal walls beneath the original concrete roof at the Old School House
Stripped internal walls beneath the original concrete roof at the Old School House
Temporary props inside the Old School House during structural preparation
Temporary props inside the Old School House during structural preparation
Existing concrete roof during removal work at the Old School House in South Kyme
Existing concrete roof during removal work at the Old School House in South Kyme
Concrete roof section being lifted away at the Old School House in South Kyme
Concrete roof section being lifted away at the Old School House in South Kyme